What Download PMP Training Is
Proper study guides for Update PMP Project Management Professional certified begins with PMP PMP preparation products which designed to deliver the Practical PMP questions by making you pass the PMP test at your first time. Try the free PMP demo right now.
Online PMP PMP free dumps demo Below:
NEW QUESTION 1
In a typical project, project managers spend most of their time:
- A. Estimating
- B. Scheduling
- C. Controlling
- D. Communicating
Answer: D
NEW QUESTION 2
As part of a mid-project evaluation, the project sponsor has asked for a forecast of the total project cost. What should be used to calculate the forecast?
- A. BAC
- B. EAC
- C. ETC
- D. WBS
Answer: B
NEW QUESTION 3
Which input to Collect Requirements is used to identify stakeholders who can provide information on requirements?
- A. Stakeholder register
- B. Scope management plan
- C. Stakeholder management plan
- D. Project charter
Answer: A
NEW QUESTION 4
The ways in which the roles and responsibilities, reporting relationships, and staffing management will be addressed and structured within a project is described in the:
- A. Human resource management plan.
- B. Activity resource requirements.
- C. Personnel assessment tools,
- D. Multi-criteria decision analysis.
Answer: A
NEW QUESTION 5
A reward can only be effective if it is:
- A. Given immediately after the project is completed.
- B. Something that is tangible.
- C. Formally given during project performance appraisals.
- D. Satisfying a need valued by the individual.
Answer: D
NEW QUESTION 6
A tool and technique used in the Develop Project Charter process is:
- A. change control tools
- B. expert judgment
- C. meetings
- D. analytical techniques
Answer: B
NEW QUESTION 7
Which of the following is an output of Close Procurements?
- A. Accepted deliverables
- B. Organizational process assets updates
- C. Managing stakeholder expectations
- D. Performance reports
Answer: B
NEW QUESTION 8
What defines the portion of work included in a contract for items being purchased or acquired?
- A. Procurement management plan
- B. Evaluation criteria
- C. Work Breakdown Structure (WBS)
- D. Contract Statement of Work (SOW)
Answer: D
NEW QUESTION 9
Which process documents the business needs of a project and the new product, service, or other result that is intended to satisfy those requirements?
- A. Develop Project Management Plan
- B. Develop Project Charter
- C. Direct and Manage Project Execution
- D. Collect Requirements
Answer: B
NEW QUESTION 10
What is the total float of the critical path?
- A. Can be any number
- B. Zero or positive
- C. Zero or negative
- D. Depends on the calendar
Answer: C
NEW QUESTION 11
The following chart contains information about the tasks in a project.
Based on the chart, what is the cost performance index (CPI) for Task 2?
- A. 0.8
- B. 1
- C. 1.25
- D. 1.8
Answer: C
NEW QUESTION 12
Which of the following is an output of the Perform Integrated Change Control process?
- A. Project document updates
- B. Organizational process assets updates
- C. Change requests
- D. Deliverables
Answer: A
NEW QUESTION 13
Which of the following tools or techniques is used for Estimate Activity Duration?
- A. Critical path
- B. Rolling Wave
- C. PDM
- D. Para metric
Answer: D
NEW QUESTION 14
What is the name of a graphic display of project team members and their reporting relationships?
- A. Role dependencies chart
- B. Reporting flow diagram
- C. Project organization chart
- D. Project team structure diagram
Answer: C
NEW QUESTION 15
The Human Resource Management processes are:
- A. Develop Human Resource Plan, Acquire Project Team, Develop Project Team, and Manage Project Team.
- B. Acquire Project Team, Manage Project Team, Manage Stakeholder Expectations, and Develop Project Team.
- C. Acquire Project Team, Develop Human Resource Plan, Conflict Management, and Manage Project Team.
- D. Develop Project Team, Manage Project Team, Estimate Activity Resources, and Acquire Project Team.
Answer: A
NEW QUESTION 16
Perform Integrated Change Control is the process of:
- A. Reviewing, approving, and managing all change requests
- B. Facilitating change management, manuals, or automation tools
- C. Comparing actual results with planned results in order to expand or change a project
- D. Documenting changes according to the change control system by the change control board
Answer: A
NEW QUESTION 17
Ensuring that projects and programs are reviewed to prioritize resource allocation is a focus of which of the following?
- A. Project management
- B. Program management
- C. Portfolio management
- D. Relationship management
Answer: C
NEW QUESTION 18
What tool and technique is used to determine whether work and deliverables meet requirements and product acceptance criteria?
- A. Decomposition
- B. Benchmarking
- C. Inspection
- D. Checklist analysis
Answer: C
NEW QUESTION 19
Which element does a project charter contain?
- A. Management reserves
- B. Work breakdown structure
- C. Stakeholder list
- D. Stakeholder register
Answer: C
NEW QUESTION 20
The individual or group that provides resources and support for a project and is accountable for success is the:
- A. sponsor
- B. customer
- C. business partners
- D. functional managers
Answer: A
NEW QUESTION 21
Regression analysis, failure mode and effect analysis (FMEA), fault tree analysis (FTA), and trend analysis are examples of which tool or technique?
- A. Expert judgment
- B. Forecasting methods
- C. Earned value management
- D. Analytical techniques
Answer: D
NEW QUESTION 22
An input of the Plan Procurement Management process is:
- A. Make-or-buy decisions.
- B. Activity cost estimates.
- C. Seller proposals.
- D. Procurement documents.
Answer: B
NEW QUESTION 23
An output of the Manage Project Team process is:
- A. project management plan updates
- B. project staff assignments updates
- C. team performance assessments
- D. resource calendar updates
Answer: A
NEW QUESTION 24
Typical outcomes of a project include:
- A. Products, services, and improvements.
- B. Products, programs, and services.
- C. Improvements, portfolios, and services.
- D. Improvements, processes, and products.
Answer: A
NEW QUESTION 25
Which enterprise environmental factors are considered during Estimate Costs?
- A. Market conditions and published commercial information
- B. Company structure and market conditions
- C. Commercial information and company structure
- D. Existing human resources and market conditions
Answer: A
NEW QUESTION 26
......
Recommend!! Get the Full PMP dumps in VCE and PDF From Thedumpscentre.com, Welcome to Download: https://www.thedumpscentre.com/PMP-dumps/ (New 918 Q&As Version)