NEW QUESTION 1
Which should be provided by a project mandate?
- A. Terms of reference
- B. Detailed Business Case
- C. Stage tolerances
- D. Initiation Stage Plan
Answer: A
NEW QUESTION 2
Which should be funded by a change budget?
- A. Increase in agreed scope
- B. Initiation stage
- C. Change Authority
- D. Handover activities
Answer: A
NEW QUESTION 3
Which is a purpose of a Product Description?
- A. Provide the cost tolerance available for individual products
- B. Define reporting frequency
- C. Record the quality checks completed for the End Stage Report
- D. Document the level of quality required of a product
Answer: D
NEW QUESTION 4
Which activity takes place within the Managing a Stage Boundary process?
- A. Produce Highlight Reports
- B. Take corrective action within the limits of a stage's tolerance
- C. Produce an Exception Plan
- D. Authorize a Stage Plan for the next stage
Answer: C
NEW QUESTION 5
Which product identifies the management stages and timescales of a project?
- A. Project Brief
- B. Project Product Description
- C. Project Plan
- D. Initiation Stage Plan
Answer: C
NEW QUESTION 6
Which of the following statements about the Closing a Project process are true?
1. The Closing a Project process provides a fixed point for the receipt of completed Work Packages for the work performed in the final stage.
2. The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved. Packages for the work performed in the final stage.
- A. Only 1 is true
- B. Only 2 is true
- C. Both 1 and 2 aretrue
- D. Neither 1 or 2 are true
Answer: B
NEW QUESTION 7
Which theme addresses the need to have a strategy for communicating with stakeholders?
- A. Quality
- B. Organization
- C. Plans
- D. Progress
Answer: B
NEW QUESTION 8
Which is the base product against which the Project Board can assess progress, issues and ongoing viability questions?
- A. Project Brief
- B. Project Initiation Documentation
- C. Project mandate
- D. Benefits Review Plan
Answer: B
NEW QUESTION 9
Who carries out audits that are independent of the project?
- A. Quality assurance
- B. Project Assurance
- C. Project Support
- D. Project Manager
Answer: A
NEW QUESTION 10
Identify the missing words in the following sentence. The purpose of the Starting up a Project process is as much about [?] as it is about requesting authorization to initiate viable
projects,
- A. producing an achievable Project Plan
- B. preventing poorly-conceived projects from ever being initiated
- C. obtaining approval from all stakeholders
- D. setting up the required project controls
Answer: B
NEW QUESTION 11
How many roles make up the Project Board?
- A. One
- B. Two
- C. Three
- D. Four
Answer: C
NEW QUESTION 12
Which role does NOT set tolerances?
- A. Corporate or programme management
- B. Project Board
- C. Change Authority
- D. Project Manager
Answer: C
NEW QUESTION 13
Which is a purpose of quality planning?
- A. Define the structure of the project management team
- B. Detail the acceptance criteria, in order for the Project Board to agree the level of qualityexpected of the project's product
- C. Document approval records for those project products that have met their quality criteria
- D. Produce the Project Plan with resource and schedule information
Answer: B
NEW QUESTION 14
What is a purpose of a Benefits Review Plan?
- A. Provide information regarding unfinished work to the group which will support the project's products in their operational life
- B. Give a detailed analysis of only those benefits that were realized before the project closed
- C. Document the justification for undertaking the project, based on the estimated costs versus the anticipated benefits
- D. Provide details of the time and effort needed to carry out the planned benefits reviews
Answer: D
NEW QUESTION 15
Which is a purpose of a Lessons Report?
- A. Improve the project management method for future projects
- B. Detail open issues and risks that need to be managed after the project has closed
- C. Compare the actual performance of the final stage against its plan
- D. Provide a summary of the benefits realized during the project
Answer: A
NEW QUESTION 16
Which is the Issue Register NOT used for?
- A. Capture external events that are impacting a stage
- B. Record information about a deviation in stage tolerance
- C. Capture any threats or opportunities that might have an impact on astage
- D. Record any problems identified when authorizing a Work Package
Answer: C
NEW QUESTION 17
Identify the missing word in the following sentence. A member of the Project Board is responsible for [ ? ] assurance.
- A. quality
- B. supplier
- C. risk
- D. product
Answer: B
NEW QUESTION 18
Which is assumed to be a supplier's responsibility in the PRINCE2 customer/supplier environment?
- A. Specify the desired result
- B. Provide the resources and skills to deliver the desired result
- C. Pay for the project
- D. Specify the benefits of the project
Answer: B
NEW QUESTION 19
What should influence the Project Board's decision whether to delegate its Project Assurance responsibilities?
- A. The preference of the Project Manager
- B. Having insufficient authority to perform the role
- C. Having insufficient time to perform the role
- D. The need to involve key stakeholders on the project management team
Answer: C
NEW QUESTION 20
Which is shown in a product breakdown structure?
- A. Management stages, major products and control points
- B. In which order the products should be created
- C. The major products that are to be developed in a plan
- D. What resources are required to develop the products
Answer: C
NEW QUESTION 21
Why is it crucial that the Project Product Description clearly defines acceptance methods?
- A. Enables Project Assurance to authorize quality activities
- B. Defines how all project products will be reviewed and approved
- C. Defines how it will be proven that the completed project product meets the customer's expectations
- D. Provides confirmation that all project products have met their quality criteria
Answer: C
NEW QUESTION 22
Who represents the three project interests on a project?
- A. Project Manager
- B. Project Support
- C. External project stakeholders
- D. Project Board
Answer: D
NEW QUESTION 23
Which is one of the three levels of plan in PRINCE2?
- A. Benefits Review Plan
- B. Programme Plan
- C. Team Plan
- D. Project Brief
Answer: C
NEW QUESTION 24
Which role is responsible for creating Checkpoint Reports?
- A. Senior Supplier
- B. Team Manager
- C. Change Authority
- D. Project Support
Answer: B
NEW QUESTION 25
How is a Benefits Review Plan used in the Closing a Project process?
- A. Checked for inclusion of activities to confirm those benefits which cannot be measured until after project closure
- B. To capture the baseline measures against which to assess benefits
- C. To capture side-effects (beneficial or adverse) identified during post-project benefits reviews
- D. To gain approval for the post-project activities and transferresponsibility to corporate or programme management
Answer: A
NEW QUESTION 26
If a project's benefit tolerance is forecast to be exceeded, to whom should this be escalated to for a decision?
- A. Senior User
- B. Executive
- C. Corporate/programme management
- D. Senior Supplier
Answer: C
NEW QUESTION 27
Which does NOT reflect the PRINCE2 principle of continued business justification?
- A. There must be a justifiable reason for starting a project
- B. The business justification drives decision making
- C. If a project is no longer forecast to deliver a financial benefit, it should be stopped.
- D. If a project can no longer be justified, it should be stopped
Answer: C
NEW QUESTION 28
Which should be funded from a change budget?
- A. The Starting up a Project process
- B. A fallback plan
- C. An agreed change to the scope of a project
- D. A change to a plan, within allocated tolerances, due to poor estimating
Answer: C
NEW QUESTION 29
Which process provides the Project Board with the information it requires in order to commit
resources to the project?
- A. Managing Product Delivery
- B. Initiating a Project
- C. Controlling a Stage
- D. Directinga Project
Answer: B
NEW QUESTION 30
Which risk response type is appropriate to respond to an opportunity?
- A. Accept
- B. Fallback
- C. Exploit
- D. Transfer
Answer: C
NEW QUESTION 31
......
100% Valid and Newest Version PRINCE2-Foundation Questions & Answers shared by Certshared, Get Full Dumps HERE: https://www.certshared.com/exam/PRINCE2-Foundation/ (New 296 Q&As)