NEW QUESTION 1

The stakeholder register is an output of:

  • A. Identify Stakeholders.
  • B. Plan Stakeholder Management.
  • C. Control Stakeholder Engagement.
  • D. Manage Stakeholder Engagemen

Answer: A

NEW QUESTION 2

At the start of a typical project life cycle, costs are:

  • A. low, peak as work is carried out, and drop as the project nears the end.
  • B. low, become steady as work is carried out, and increase as the project nears the end.
  • C. high, drop as work is carried out, and increase as the project nears the end.
  • D. high, become low as work is carried out, and drop as the project nears the en

Answer: A

NEW QUESTION 3

Analogous cost estimating relies on which of the following techniques?

  • A. Expert judgment
  • B. Project management software
  • C. Vendor bid analysis
  • D. Reserve analysis

Answer: A

NEW QUESTION 4

Which item is a cost of conformance?

  • A. Training
  • B. Liabilities
  • C. Lost business
  • D. Scrap

Answer: A

NEW QUESTION 5

In complex projects/ initiating processes should be completed:

  • A. Within a work package.
  • B. In each phase of the project.
  • C. To estimate schedule constraints.
  • D. To estimate resource allocation

Answer: B

NEW QUESTION 6

Which tool or technique of the Define Activities process allows for work to exist at various levels of detail depending on where it is in the project life cycle?

  • A. Historical relationships
  • B. Dependency determination
  • C. Bottom-up estimating
  • D. Rolling wave planning

Answer: D

NEW QUESTION 7

An issue log is an input to which Project Human Resource Management process?

  • A. Manage Project Team
  • B. Acquire Project Team
  • C. Plan Human Resource Management
  • D. Develop Project Team

Answer: A

NEW QUESTION 8

An input of the Plan Procurement Management process is:

  • A. Make-or-buy decisions.
  • B. Activity cost estimates.
  • C. Seller proposals.
  • D. Procurement document

Answer: B

NEW QUESTION 9

Which can be used to determine whether a process is stable or has predictable performance?

  • A. Matrix diagram
  • B. Histogram
  • C. Control chart
  • D. Flowchart

Answer: C

NEW QUESTION 10

In a construction project schedule, what is the logical relationship between the delivery of the concrete materials and the pouring of concrete?

  • A. Start-to-start (SS)
  • B. Start-to-finish (SF)
  • C. Rnish-to-finish (FF)
  • D. Finish-to-start (FS)

Answer: D

NEW QUESTION 11

Progressively elaborating high-level information into detailed plans is performed by the:

  • A. project management office
  • B. portfolio manager
  • C. program manager
  • D. project manager

Answer: D

NEW QUESTION 12

Which earned value management (EVM) metric is a measure of the cost efficiency of budgeted resources expressed as a ratio of earned value (EV) to actual cost (AC) and is considered a critical EVM metric?

  • A. Cost variance (CV)
  • B. Cost performance index (CPI)
  • C. Budget at completion (BAC)
  • D. Variance at completion (VAC)

Answer: B

NEW QUESTION 13

One of the key benefits of the Plan Human Resource Management process is that it:

  • A. outlines team selection guidelines and team member responsibilities.
  • B. establishes project roles and responsibilities.
  • C. improves teamwork, interpersonal skills, and competencies.
  • D. provides an accurate appraisal of team member performanc

Answer: B

NEW QUESTION 14

Which tool or technique is used in the Develop Project Management Plan process?

  • A. Pareto diagram
  • B. Performance reporting
  • C. SWOT analysis
  • D. Expert judgment

Answer: D

NEW QUESTION 15

A project has a current cost performance index (CPI) of 1.25. To date, US$10,000 have been spent on performing the project work. What is the earned value of the work completed to date?

  • A. US$S000
  • B. US$9500
  • C. US$10,000
  • D. US$12,500

Answer: D

NEW QUESTION 16

Which of the following statements correctly characterizes pull communication?

  • A. It includes letters, memos, reports, emails, and faxes.
  • B. It requires recipients to access communication content at their own discretion.
  • C. It is the most efficient way to ensure a common understanding among all participants.
  • D. It is primarily used when the volume of information to be transferred is minima

Answer: B

NEW QUESTION 17

Another name for an Ishikawa diagram is:

  • A. cause and effect diagram.
  • B. control chart.
  • C. flowchart.
  • D. histogra

Answer: A

NEW QUESTION 18

The technique of subdividing project deliverables into smaller, more manageable components until the work and deliverables are defined to the work package level is called:

  • A. a control chart.
  • B. baseline.
  • C. Create WBS.
  • D. decompositio

Answer: D

NEW QUESTION 19

Which Knowledge Area is concerned with the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information?

  • A. Project Integration Management
  • B. Project Communications Management
  • C. Project Information Management System (PIMS)
  • D. Project Scope Management

Answer: B

NEW QUESTION 20

An output of the Direct and Manage Project Work process is:

  • A. Deliverables.
  • B. Activity lists.
  • C. A work breakdown structure.
  • D. A scope statemen

Answer: A

NEW QUESTION 21
......

P.S. Easily pass CAPM Exam with 704 Q&As Thedumpscentre.com Dumps & pdf Version, Welcome to Download the Newest Thedumpscentre.com CAPM Dumps: https://www.thedumpscentre.com/CAPM-dumps/ (704 New Questions)