Renovate Certified Associate In Project Management (PMI-100) CAPM Exams
It is impossible to pass PMI CAPM exam without any help in the short term. Come to Ucertify soon and find the most advanced, correct and guaranteed PMI CAPM practice questions. You will get a surprising result by our Renewal Certified Associate in Project Management (PMI-100) practice guides.
PMI CAPM Free Dumps Questions Online, Read and Test Now.
NEW QUESTION 1
The stakeholder register is an output of:
- A. Identify Stakeholders.
- B. Plan Stakeholder Management.
- C. Control Stakeholder Engagement.
- D. Manage Stakeholder Engagemen
Answer: A
NEW QUESTION 2
At the start of a typical project life cycle, costs are:
- A. low, peak as work is carried out, and drop as the project nears the end.
- B. low, become steady as work is carried out, and increase as the project nears the end.
- C. high, drop as work is carried out, and increase as the project nears the end.
- D. high, become low as work is carried out, and drop as the project nears the en
Answer: A
NEW QUESTION 3
Analogous cost estimating relies on which of the following techniques?
- A. Expert judgment
- B. Project management software
- C. Vendor bid analysis
- D. Reserve analysis
Answer: A
NEW QUESTION 4
Which item is a cost of conformance?
- A. Training
- B. Liabilities
- C. Lost business
- D. Scrap
Answer: A
NEW QUESTION 5
In complex projects/ initiating processes should be completed:
- A. Within a work package.
- B. In each phase of the project.
- C. To estimate schedule constraints.
- D. To estimate resource allocation
Answer: B
NEW QUESTION 6
Which tool or technique of the Define Activities process allows for work to exist at various levels of detail depending on where it is in the project life cycle?
- A. Historical relationships
- B. Dependency determination
- C. Bottom-up estimating
- D. Rolling wave planning
Answer: D
NEW QUESTION 7
An issue log is an input to which Project Human Resource Management process?
- A. Manage Project Team
- B. Acquire Project Team
- C. Plan Human Resource Management
- D. Develop Project Team
Answer: A
NEW QUESTION 8
An input of the Plan Procurement Management process is:
- A. Make-or-buy decisions.
- B. Activity cost estimates.
- C. Seller proposals.
- D. Procurement document
Answer: B
NEW QUESTION 9
Which can be used to determine whether a process is stable or has predictable performance?
- A. Matrix diagram
- B. Histogram
- C. Control chart
- D. Flowchart
Answer: C
NEW QUESTION 10
In a construction project schedule, what is the logical relationship between the delivery of the concrete materials and the pouring of concrete?
- A. Start-to-start (SS)
- B. Start-to-finish (SF)
- C. Rnish-to-finish (FF)
- D. Finish-to-start (FS)
Answer: D
NEW QUESTION 11
Progressively elaborating high-level information into detailed plans is performed by the:
- A. project management office
- B. portfolio manager
- C. program manager
- D. project manager
Answer: D
NEW QUESTION 12
Which earned value management (EVM) metric is a measure of the cost efficiency of budgeted resources expressed as a ratio of earned value (EV) to actual cost (AC) and is considered a critical EVM metric?
- A. Cost variance (CV)
- B. Cost performance index (CPI)
- C. Budget at completion (BAC)
- D. Variance at completion (VAC)
Answer: B
NEW QUESTION 13
One of the key benefits of the Plan Human Resource Management process is that it:
- A. outlines team selection guidelines and team member responsibilities.
- B. establishes project roles and responsibilities.
- C. improves teamwork, interpersonal skills, and competencies.
- D. provides an accurate appraisal of team member performanc
Answer: B
NEW QUESTION 14
Which tool or technique is used in the Develop Project Management Plan process?
- A. Pareto diagram
- B. Performance reporting
- C. SWOT analysis
- D. Expert judgment
Answer: D
NEW QUESTION 15
A project has a current cost performance index (CPI) of 1.25. To date, US$10,000 have been spent on performing the project work. What is the earned value of the work completed to date?
- A. US$S000
- B. US$9500
- C. US$10,000
- D. US$12,500
Answer: D
NEW QUESTION 16
Which of the following statements correctly characterizes pull communication?
- A. It includes letters, memos, reports, emails, and faxes.
- B. It requires recipients to access communication content at their own discretion.
- C. It is the most efficient way to ensure a common understanding among all participants.
- D. It is primarily used when the volume of information to be transferred is minima
Answer: B
NEW QUESTION 17
Another name for an Ishikawa diagram is:
- A. cause and effect diagram.
- B. control chart.
- C. flowchart.
- D. histogra
Answer: A
NEW QUESTION 18
The technique of subdividing project deliverables into smaller, more manageable components until the work and deliverables are defined to the work package level is called:
- A. a control chart.
- B. baseline.
- C. Create WBS.
- D. decompositio
Answer: D
NEW QUESTION 19
Which Knowledge Area is concerned with the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information?
- A. Project Integration Management
- B. Project Communications Management
- C. Project Information Management System (PIMS)
- D. Project Scope Management
Answer: B
NEW QUESTION 20
An output of the Direct and Manage Project Work process is:
- A. Deliverables.
- B. Activity lists.
- C. A work breakdown structure.
- D. A scope statemen
Answer: A
NEW QUESTION 21
......
P.S. Easily pass CAPM Exam with 704 Q&As Thedumpscentre.com Dumps & pdf Version, Welcome to Download the Newest Thedumpscentre.com CAPM Dumps: https://www.thedumpscentre.com/CAPM-dumps/ (704 New Questions)