A Review Of Printable CAPM Pdf Exam

we provide Real PMI CAPM test questions which are the best for clearing CAPM test, and to get certified by PMI Certified Associate in Project Management (PMI-100). The CAPM Questions & Answers covers all the knowledge points of the real CAPM exam. Crack your PMI CAPM Exam with latest dumps, guaranteed!

Online CAPM free questions and answers of New Version:

NEW QUESTION 1

A collection of projects managed as a group to achieve strategic objectives is referred to as a:

  • A. plan
  • B. process
  • C. program
  • D. portfolio

Answer: D

NEW QUESTION 2

Skills necessary for project management such as motivating to provide encouragement; listening actively; persuading a team to perform an action; and summarizing, recapping, and identifying next steps are known as:

  • A. organizational skills
  • B. technical skills
  • C. communication skills
  • D. hard skills

Answer: C

NEW QUESTION 3

Typical outcomes of a project include:

  • A. Products, services, and improvements.
  • B. Products, programs, and services.
  • C. Improvements, portfolios, and services.
  • D. Improvements, processes, and product

Answer: A

NEW QUESTION 4

Which of the following is an output of the Distribute Information process?

  • A. Project calendar
  • B. Communications management plan
  • C. Organizational process assets updates
  • D. Project document updates

Answer: C

NEW QUESTION 5

The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected: Actual cost = $50,000, Plan cost = $45,000, Earned value = $40,000. What is the cost performance index?

  • A. 0.8
  • B. 0.89
  • C. 1.13
  • D. 1.25

Answer: A

NEW QUESTION 6

Activity cost estimates and the project schedule are inputs to which Project Cost Management process?

  • A. Estimate Costs
  • B. Control Costs
  • C. Plan Cost Management
  • D. Determine Budget

Answer: D

NEW QUESTION 7

Which quality control technique illustrates the 80/20 principle?

  • A. Ishikawa diagram
  • B. Control chart
  • C. Run chart
  • D. Pareto chart

Answer: D

NEW QUESTION 8

Which is an input to the Verify Scope process?

  • A. Performance report
  • B. Work breakdown structure (WBS)
  • C. Requested changes
  • D. Project management plan

Answer: D

NEW QUESTION 9

What are the Project Procurement Management processes?

  • A. Conduct Procurements, Control Procurements, Integrate Procurements, and Close Procurements
  • B. Estimate Procurements, Integrate Procurements, Control Procurements, and Validate Procurements
  • C. Plan Procurement Management, Conduct Procurements, Control Procurements, and Close Procurements
  • D. Plan Procurement Management, Perform Procurements, Control Procurements, and Validate Procurements

Answer: C

NEW QUESTION 10

Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?

  • A. Procurement documents
  • B. Communications plan
  • C. Project charter
  • D. Stakeholder register

Answer: C

NEW QUESTION 11

A tool and technique used during the Collect Requirements process is:

  • A. prototypes.
  • B. expert judgment.
  • C. alternatives identification.
  • D. product analysi

Answer: A

NEW QUESTION 12

What is the definition of Direct and Manage Project Execution?

  • A. Integrating all planned activities
  • B. Performing the activities included in the plan
  • C. Developing and maintaining the plan
  • D. Execution of deliverables

Answer: B

NEW QUESTION 13

The Plan Stakeholder Management process belongs to which Process Group?

  • A. Executing
  • B. Initiating
  • C. Planning
  • D. Monitoring and Controlling

Answer: C

NEW QUESTION 14

How many Project Management Process Groups are there?

  • A. 3
  • B. 4
  • C. 5
  • D. 6

Answer: C

NEW QUESTION 15

Which Process Group's purpose is to track, review, and regulate the progress and performance of the project; identify any areas in which changes to the plan are required; and initiate the corresponding changes?

  • A. Monitoring and Controlling
  • B. Initiating
  • C. Planning
  • D. Executing

Answer: A

NEW QUESTION 16

Which tool or technique is used to develop the human resource management plan?

  • A. Ground rules
  • B. Expert judgment
  • C. Team-building activities
  • D. Interpersonal skills

Answer: B

NEW QUESTION 17

Which basic quality tool explains a change in the dependent variable in relationship to a change observed in the corresponding independent variable?

  • A. Cause-and-effect diagram
  • B. Histogram
  • C. Control chart
  • D. Scatter diagram

Answer: D

NEW QUESTION 18

Which of the following is an enterprise environmental factor that can influence the Develop Project Charter process?

  • A. Organizational standard processes
  • B. Marketplace conditions
  • C. Historical information
  • D. Templates

Answer: B

NEW QUESTION 19

When a permitting agency takes longer than planned to issue a permit, this can be described as a risk:

  • A. event.
  • B. response,
  • C. perception.
  • D. impac

Answer: A

NEW QUESTION 20

A strengths, weaknesses, opportunities, and threats (SWOT) analysis is a tool or technique used in which process?

  • A. Identify Risks
  • B. Control Risks
  • C. Perform Quantitative Risk Analysis
  • D. Perform Qualitative Risk Analysis

Answer: A

NEW QUESTION 21
......

100% Valid and Newest Version CAPM Questions & Answers shared by DumpSolutions.com, Get Full Dumps HERE: https://www.dumpsolutions.com/CAPM-dumps/ (New 704 Q&As)