Examcollection ISEB-SWT2 Questions are updated and all ISEB-SWT2 answers are verified by experts. Once you have completely prepared with our ISEB-SWT2 exam prep kits you will be ready for the real ISEB-SWT2 exam without a problem. We have Up to date ISEB ISEB-SWT2 dumps study guide. PASSED ISEB-SWT2 First attempt! Here What I Did.
Check ISEB-SWT2 free dumps before getting the full version:
NEW QUESTION 1
Why is independent testing important? [K1]
- A. Because independent testers make fewer assumptions than developers
- B. Because independent testers are isolated from the development team
- C. Because independent testers can verify assumptions made during specification and implementation of the system
- D. Because independent testers have a greater sense of responsibility for quality than developers
Answer: C
NEW QUESTION 2
Of the following, select the best description of the fundamental test process:
- A. Planning and control, analysis, design, implementation, execution, evaluation of exit criteria and reporting, test closure.
- B. Executing tests, identifying and recording defects and preparing recommendation and closure reports.
- C. Controls, preparation of test cases, execution of test cases, execution of regression packs, communicating with developers, writing recommendations for release.
- D. Static testing, dynamic testing, defect reporting, reporting and closure.
Answer: A
NEW QUESTION 3
The introduction of reviews and inspections has often failed as a process improvement action. Identify the THREE most important measures that should be taken to reduce the risk that this test process improvement will fail. 2 Credits (for 2 out of 3 correct 1 credit)
- A. Process ownership and experienced moderators who drive the inspection process.
- B. Management support
- C. Training of those involved
- D. The availability of stands and processes
- E. Usage of a more traditional software development lifecycle
- F. Alignment with software process improvement
- G. Using a reference model, e.
- H. TMMi
Answer: ABC
NEW QUESTION 4
The following statements relate to activities that are part of the fundamental test process.
- A. Evaluating the testability of requirements.i
- B. Repeating testing activities after changes.ii
- C. Designing the test environment set-up.i
- D. Developing and prioritizing test cases.
- E. Verifying the environment is set up correctly.Which statement below is TRUE?
- F. (i) and (ii) are part of analysis and design, (iii), (iv) and (v) are part of test implementation and execution.
- G. (i) and (iii) are part of analysis and design, (ii), (iv) and (v) are part of test implementation and execution.
- H. (i) and (v) are part of analysis and design, (ii), (iii) and (iv) are part of test implementation and execution.
- I. (i) and (iv) are part of analysis and design, (ii), (iii) and (v) are part of test implementation and execution.
Answer: B
Explanation:
All other answers contain an activity identified as analysis and design that is part of implementation and test execution.
NEW QUESTION 5
Which of the following is correct? Debugging is:
- A. Testing/checking whether the software performs correctly.
- B. Checking that a previously reported defect has been corrected.
- C. Identifying the cause of a defect, repairing the code and checking the fix is correct.
- D. Checking that no unintended consequences have occurred as a result of a fix.
Answer: C
Explanation:
* A. Is a brief definition of testing.
* B. Is retesting.
* D. Is regression testing.
NEW QUESTION 6
Which type of review has the following main purposes:
discussing, making decisions, evaluating alternatives, finding defects, solving technical problems and checking conformance to specifications, plans, regulations, and standards?
- A. Technical Review
- B. Inspection
- C. Walkthrough
- D. Informal review
Answer: A
NEW QUESTION 7
Which of the following statements are true?
(i) For every development activity there is a corresponding testing activity.
(ii) Each test level has the same test objectives.
(iii) The analysis and design of tests for a given test level should begin after the corresponding development activity.
(iv) Testers should be involved in reviewing documents as soon as drafts are available in the development life cycle.
- A. (i) and (ii)
- B. (iii) and (iv)
- C. (ii) and (iii)
- D. (i) and (iv)
Answer: D
Explanation:
Option (ii) is incorrect: each test level has a different objective.
Option (iii) is also incorrect: test analysis and design should start once the documentation has been completed.
NEW QUESTION 8
Incorrect form of Logic coverage is:
- A. Statement Coverage
- B. Pole Coverage
- C. Condition Coverage
- D. Path Coverage
Answer: B
NEW QUESTION 9
System testing is:
- A. Used to search for defects in software modules that are separately testable.
- B. The responsibility of the users of a system.
- C. Concerned with the behavior of a whole system/product as defined by the scope of a developmentproject.
- D. Triggered by modifications, migration or retirement of the software system.
Answer: C
NEW QUESTION 10
What is the Risk Priority Number for risk item number 2? 2 credits
- A. 16
- B. 2
- C. 1
- D. 63
Answer: D
NEW QUESTION 11
Which statement is most true?
- A. Different testing is needed depending upon the application.
- B. All software is tested in the same way.
- C. A technique that finds defects will always find defects.
- D. A technique that has found no defects is not useful.
Answer: A
Explanation:
This is a restatement of the testing principle ‘Testing is context dependent’
NEW QUESTION 12
Which of the main activities of the fundamental test process does the task ‘verify the test environment set up is correct’ relate to? [K1]
- A. Planning and control
- B. Analysis and design
- C. Implementation and execution
- D. Evaluating exit criteria and reporting
Answer: C
NEW QUESTION 13
You have investigated different possibilities and selected four of them to present to IT management. Which of the proposals will you most likely give your highest recommendations? 3 credits
- A. Insourcing of test automation based on an offer from a local company ABC that has people who are specialists in system level capture-replay automation tools and they also do regular training courses in test automation methods and tool
- B. They can then work closely with Vicki.
- C. Outsourcing of test automation based on an offer from an Asian company, AsiaAutoTest, which has people who are specialists in system level capture-replay automation tool
- D. They also offer training and besides they offer to run and maintain the regression tests in the future.
- E. Internal offer from the development department of XYZ to create the regression package using CppUnit as test automation too
- F. One of the development groups have very good experiences in automating unit tests, and they are willing to do training as well.
- G. Solution from a tool vendor offering to educate two test team members in the use of their easy-to-use test automation capture replay tool over the first 3 month and based on that build the regression test suit
- H. In addition to Vicki, Steve is the only one that has time available to be educated.
Answer: A
NEW QUESTION 14
Relying only on the information provided in the scenario, select the TWO items and/or features for which sufficient information is available to proceed with test design. 2 credits
- A. All supported credit cards
- B. Language localization
- C. Valid and invalid advances
- D. Usability
- E. Response time
Answer: AC
NEW QUESTION 15
Which of the following, if observed in reviews and tests, would lead to problems (or conflict) within teams?
- A. Testers and reviewers are not curious enough to find defects.
- B. Testers and reviewers are not qualified enough to find failures and faults.
- C. Testers and reviewers communicate defects as criticism against persons and not against the software product.
- D. Testers and reviewers expect that defects in the software product have already been found and fixed by the developers.
Answer: C
NEW QUESTION 16
The selection of test cases for regression testing..?
- A. Requires knowledge on the bug fixes and how it affect the system
- B. Includes the area of frequent defects
- C. Includes the area which has undergone many/recent code changes
- D. All of the above
Answer: D
NEW QUESTION 17
Test script TransVal 3.1 tests transaction validation via screen TRN 003B. According to the specification (PID ver 1.3 10b iv) the validation screen should not accept future dated transactions. Test script TransVal 3.1 passes. Test script eod 1.4 tests end of day processing and is run after the execution of TransVal 3.1 using data entered during that test
Which of the following is the BEST detail on an incident report? [K3]
- A. Titl
- B. End of Day failure.. Reproducibl
- C. Ye
- D. Descriptio
- E. Script eod 1.4 fails when the first transaction of the day is a future dated transactio
- F. Screen shot of the failure attached.
- G. Titl
- H. Transaction input screen validation..Reproducibl
- I. Ye
- J. Descriptio
- K. Script eod 1..4 fails . Screen shot of the failure attache
- L. Validation of transaction entryon screen TRN-003B should not allow future dated transactions – see PID ver 1.3 para 10b iv.
- M. Titl
- N. Screen TRN-003B validation of transaction date.. Reproducibl
- O. N
- P. Descriptio
- Q. When a future dated transaction is processed by the end of day process, a failure can occu
- R. This does not always happe
- S. Screen shot of the failure attached.
- T. Titl
- . Screen TRN-003B validation of transaction dat
- . Reproducibl
- . Ye
- . Descriptio
- . Script eod 1.4 fails when the first transaction of the day is a future dated transactio
- . Screen shot of the failure attache
- . Validation of transaction entry on screen TRN-003B should not allow future dated transactions– see PID ver 1.3 para 10b iv.
Answer: D
NEW QUESTION 18
Which of the following are valid test objectives?
(i)Finding defects.
(ii)Gaining confidence about the level of quality and providing information.
(iii)Preventing defects.
(iv) Debugging the code.
- A. i, ii and iii
- B. i, ii and iv
- C. ii and iii
- D. i and iv
Answer: A
NEW QUESTION 19
What can a risk-based approach to testing provide?
- A. The types of test techniques to be employed.
- B. The total tests needed to provide 100 per cent coverage.
- C. An estimation of the total cost of testing.
- D. Only that test execution is effective at reducing risk.
Answer: A
NEW QUESTION 20
Your task is to compile a test execution schedule for the current release of software. The system specification states the following logical dependencies:
• An admin user must create/amend/delete a standard user.
• A standard user is necessary to perform all other actions.
The test plan requires that re-tests must be performed first, followed by the highest priority tests. To save time, the test plan states that tests should be scheduled to create test data for the subsequent tests in the schedule.
The following test cases have been designed, with an indication of priority (1 being the highest priority) and whether the test has previously failed.
Which test execution schedule meets the test plan requirements and logical dependencies?
- A. a, d, c, b, e
- B. a, c, b, d, e
- C. e, a, b, c, d
- D. e, a, d, c, b
Answer: C
NEW QUESTION 21
The purpose of exit criteria is:
- A. Define when to stop testing
- B. End of test level
- C. When a set of tests has achieved a specific pre condition
- D. All of the above
Answer: D
NEW QUESTION 22
Which TWO of the following test tools would be classified as test execution tools? [K2]
* a. Test data preparation tools
* b. Test harness
* c. Review tools
* d. Test comparators
* e. Configuration management tools
- A. a and b
- B. c and d
- C. c and e
- D. b and d
Answer: D
NEW QUESTION 23
A test management tool is most likely to integrate with which of the following tools?
- A. Performance testing tool
- B. Test data preparation tool
- C. Static analysis tool
- D. Requirements management tool
Answer: D
Explanation:
Requirements management tools (option (D)) often have interfaces with test management tools. In some cases they will be sold as a package or in other cases a test management tool may have its own requirements module. The use of such interfaces or integrated packages aids traceability from requirements through to test scripts and defects.
Performance management tools (option (A)), test data preparation tools (option (B)) and static analysis tools (option (C)) are unlikely to have an interface or be integrated with a test management tool. They serve different purposes and therefore there is little need for such interfaces.
NEW QUESTION 24
Which of the following factors will MOST affect the testing effort required to test a software product? [K1]
- A. The number of staff available to execute tests
- B. The level of detail in the test plan
- C. The requirements for reliability and security in the product
- D. The test estimation method used
Answer: C
NEW QUESTION 25
During test process improvement it is recommended to use standards where possible. Standards originate from various sources and they cover different subjects in relation to testing Pick TWO sources of software standards, useful to software testing from the ones mentioned below. 1 credit
- A. ISO 9126-1 ‘Software engineering- Product quality Part 1:Quality model’ is an international standard, that provides a basis on which to define quality assurance solutions.
- B. ISA 4126-1 ‘Software engineering- Product quality Part 1:Quality model’ is an international standard, that provides a basis on which to define quality assurance solutions.
- C. BS-7925-2 ‘Software testin
- D. Software component testing is a national standard used internationall
- E. It covers a number of testing techniques that may be useful both on component testing level and on system testing level.
- F. SY-395-01 ‘Standard for East Coast Hospital software’ is a regional standard adapted from a national on
- G. Besides hospital software, this standard ought to be used also by other types of software system in the region.
- H. IEEE 829 ‘standard for software test documentation’ is an international standard to be followingmandatory by all testing origination regardless of lifecycle models.
Answer: AC
NEW QUESTION 26
Which of the following statements are true?
(i) Defects are likely to be found earlier in the development process by using reviews rather than static analysis.
(ii) Walkthroughs require code but static analysis does not require code.
(iii) Informal reviews can be performed on code and specifications.
(iv) Dynamic techniques are generally used before static techniques.
(v) Dynamic techniques can only be used after code is ready to be executed.
- A. (i), (ii), (vi).
- B. (ii), (iii), (v).
- C. (i), (iv), (v).
- D. (i), (iii), (v).
Answer: D
Explanation:
The other answers are incorrect because:
(ii) Walkthroughs do not require code and static analysis does require code.
(iv) Static techniques do not execute the code and therefore can be run before and after the code is ready for execution.
NEW QUESTION 27
Test objectives for systems testing of a safety critical system include completion of all outstanding defect correction. Regression testing is required following defect correction at all test levels. Which TWO of the following metrics would be MOST suitable for determining whether the test objective has been met? [K2]
* a. Regression tests run and passed in systems testing
* b. Incidents closed in systems testing
* c. Planned tests run and passed in system testing
* d. Planned tests run and passed at all levels of testing
* e. Incidents raised and closed at all levels of testing
- A. a and e
- B. b and c
- C. d and e
- D. a and b
Answer: A
NEW QUESTION 28
Which of the following is the task of a Tester?
- A. Interaction with the Test Tool Vendor to identify best ways to leverage test tool on the project.i
- B. Prepare and acquire Test Dataii
- C. Implement Tests on all test levels, execute and log the tests.i
- D. Create the Test Specifications
- E. i, ii, iii is true and iv is false
- F. ii, iii, iv is true and i is false
- G. i is true and ii, iii, iv are false
- H. iii and iv is correct and i and ii are incorrect
Answer: B